2. Installation
18 PNEG-1615 Heavy Duty Bin Stairs and Platform Assembly for 4.00" Corrugated Bin
Figure 2R Horizontal Bracket to Step
Figure 2S Brace Strap Connection
5. Continue adding four (4) step sections until you have reached the bottom of the bin. Each of the next
wall brackets will be placed 32" lower and four (4) bolt spaces or 37-1/2" around the bin farther than
the previous bracket. See Figure 2C, Figure 2D and Figure 2E on Pages 9-11 for reference.
6. The last section to be placed on the bin will be a special bottom step section. It will include a
14" bottom wall bracket (STR1082). Use this bracket to attach the last step to the bin. An
extra brace may need to be field fabricated to tie the outside of the last step into the concrete.
Horizontal
bracket
(LDR-4083)
5/16" x 3/4" Truss head bolts
5/16" x 3/4" Truss
head bolt and nut